Phoenix Rising, OPV 2 and OPV 3

SHAH ALAM: Work for the completion of OPV2 and OPV 3 are still planning in the stage. MMEA director-general Rear Admiral (Maritime) Rosli Abdullah said the agency has issued RFI to 12 shipyards to determine the way forward for the revival of the two incomplete vessels. According to Rosli, OPV2 […]

National Security Contract

RM200 Million More To Finish OPV 2 and 3

SHAH ALAM: The Home Ministry has estimated that it need some RM200 million to complete OPV 2 and OPV 3 which are left uncomplete at the THHE Fabricators Sdn Bhd yard in Pulau Indah. Home Minister DS Shaifuddin Nasution said they had already requested the funds after checking original allocation. […]

Defence Contract

South African UAVs for MMEA’s OPVs

SHAH ALAM: As OPV1 is patrolling the South China Sea, the fact that the ship will be equipped with an UAS will certainly helped extend its range. In the press release issued by MMEA on the formal delivery of OPV1/KM Tun Fatimah early this month, it was mentioned that the […]

Defence Contract

Tender Log jam

SHAH ALAM: As we wait for the Home Ministry’s decision on how to complete MMEA’s delayed OPV2 and OPV3, we must look back at had happened within the last one year or so. And it is not very hopeful. For example, we know that the tender for four helicopters for […]